Isabela House (Construction Log 15) Progess Continues

0



We visited the construction site mid-morning today to capture some photos using my SLR digital camera and a range of lenses. The pictures do not really need captions. They simply show a team working very hard to complete our project. This blog is therefore more of a photo journal.

There was a slight hiccup yesterday when I noticed that the styrofoam insulation was missing from the preparation of the walls of the small t&b, the dirty kitchen and the kitchen. A few hasty texts and emails and the problem was addressed by our contractor. Fortunately no concrete had been poured as it would have been costly to rectify otherwise.

Read more: http://blogs.myspace.com/index.cfm?fuseaction=blog.view&friendId=495233545&blogId=525805726#ixzz11WCjUvrQ

Check out this video: Hyner House Construction 12 January 2010

You can view Andy’s MySpace Blog here: http://www.myspace.com/495233545/blog


Related Posts:

Speak Your Mind

Tell us what you're thinking...
and oh, if you want a pic to show with your comment, go get a gravatar!

CommentLuv badge