Our Philippine House Building Project House Construction Expense Report – Sept. 25, 2010 Granite installed For those of you…

Our Philippine house building project, kitchen cabinets.  We decided to follow the usual provincial Philippine method of building our kitchen cabinets.  This Philippine system for kitchen cabinets is radically different from that we’re familiar with in the U.S.  Generally, U.S. kitchens use a wood base, prefabricated cabinets which are of wood or particle board clad with a laminate or other protective finish and topped with various counter materials.  These cabinet systems are available in the bigger Philippine cities, but are expensive.  Most importantly we wonder about their durability, especially that of base cabinets, in the hot, wet, bug/fungus-infested Philippine conditions. Kitchen Counter Bases The Philippine system is a concrete skeleton; base, end panels and under counter.  In basic homes, the countertop may be tiled and the bare concrete painted…

House Construction Expense 1/1/2010 through 5/22/2010 (in U.S. Dollars) House Construction 40,904.32 Equipment 2,545.19 Labor 7,095.75 Materials 30,251.73 Soft Costs 1,011.65 OVERALL TOTAL 40,904.32 Includes stockpiled materials, almost all electrical and plumbing supplies and fixtures.  Electrical work about 50% complete.  Plumbing about 75% complete. Includes work on 35 square meter carport.  Next step finishing the walls (cement plaster) inside and out. House Construction Expense Our Philippine house building project – construction cost report as of 5-22-10. Roof completed 1/1/2010 through 5/22/2010 (in U.S. Dollars) Equipment 2,545.19 (Most to be sold at end of project. Concrete vibrator

How much does it cost to build a house in the Philippines?  Here’s our experience, month by month. February 20, 2010. Construction cost report for our Philippine House Project.   Thirty work days so far. Here’s what the house looks like after thirty days of work: After thirty work days… House Construction Expense – YTD:2 1/1/2010 through 2/21/2010 (in U.S. Dollars) Category Description 1/1/2010- 2/21/2010 House Construction 15,788.01 Equipment 2,345.72 Labor 2,489.01 Materials 10,104.24 Soft Costs 849.04 OVERALL TOTAL 15,788.01 H ouse Construction Expense Summary 1/1/2010 through 2/21/2010 (in U.S. Dollars) Equipment 2,345.72 Labor 2,489.01 Materials 10,104.24 Soft Costs (architecture, permits) 849.04 OVERALL TOTAL SO FAR: $15,788.01 Number of workers: 16 Current cost of cement: P212 ———————————————————————————————————————— March 12, 2010 construction expense report . Covers 45 work days since beginning of construction on January 18, 2010. House Construction Expense – YTD:2 1/1/2010 through 3/12/2010 (in U.S. Dollars) Category Description 1/1/2010- 3/12/2010 House Construction 22,843.05 Equipment 2,350.47 Labor 3,658.36 Materials 15,908.79 Soft Costs 925.43 OVERALL TOTAL 22,843.05 House after 45 days of work and about one million pesos. March 12, 2010 Total House Construction Expense to date  (in U.S. Dollars) Equipment 2,350.47 (10.29% of total) Labor…

Splicing error in roof beam rebar Our Philippine house building project: concrete roof beams.  This photo shows the 16mm rebar framework for the concrete roof beam which is supported by the columns and in turn will carry the considerable weight of the roof structure. For that see http://goiloilo.com/our-house-project-welding/ . A visit by our engineer confirmed a problem with the arrangement of the rebar in the beam.  Rebar comes in six meter lengths.  As shown in the photo, the workers spiced all the rebar in the center of the span.  The engineer directed that splices be staggered with no splices at mid-span in the bottom rebar and no splices at the support columns in the top of the beam. Everything you see above will have to be taken down and redone.  Our plans lacked a rebar splicing plan.  This has caused endless required corrections…

We are building a house on Panay Island in the Philippines.  We’ve documented our project with photos, text and building cost reports.  Here’s the index to our posts: A forest of bamboo scaffolding 3-10-2010 An index to posts about our Philippine house building project. A few of the links are not yet “live” but will become so as the project progresses. Our Philippine house:  Buying our lot Our Philippine house:  Building a perimeter fence Our Philippine house:  Filling the lot Our Philippine house:  House Design Our Philippine house:  Architects and builders Our Philippine house:  Digging a water well Our Philippine house:  Building a bamboo house – a “bahay kubo” Our Philippine house:  Buying construction equipment Our Philippine house:  Buying hollow block (cement …

Our Philippine house building project in Tigbauan, Iloilo. Today we had 150 cubic meters of fill delivered to our lot.  This particular …