Tuesday, September 26th, 2017

On 30th October we paid the Capital Gains Tax and Document Tax to the BIR Ilagan but as at today, 10th November, we still have not received the clearance from the BIR who also hold crucial documents we need in order to obtain our building permit from City Hall in Santiago City and register our […]

We received the first eBids for our building project on Saturday. Both were higher than expected although the smaller house was the worst coming in at the high end of the average per square meter. So we decided to do all the internal finishing ourselves with family assistance as we have all the skills represented. […]