Thursday, April 27th, 2017

After lunch we drove out with Gina’s sister to visit the construction site. The project engineer had just arrived back from a another wasted day at City Hall waiting for the City Engineer to approve the payment for and release of the building permits we applied for on 25th November. This time the excuse was […]

The switch to 24-hour operation has made a big difference and we wonder why this wasn’t done from the start. However, given that the building permit application process has been so protracted, the delay in the back fill hasn’t actually held up construction. Yesterday they redistributed and compacted around seven truck loads of fresh gravel […]