House Construction Expense 1/1/2010 through 5/22/2010 (in U.S. Dollars) House Construction 40,904.32 Equipment 2,545.19 Labor 7,095.75 Materials 30,251.73 Soft Costs 1,011.65 OVERALL TOTAL 40,904.32 Includes stockpiled materials, almost all electrical and plumbing supplies and fixtures.  Electrical work about 50% complete.  Plumbing about 75% complete. Includes work on 35 square meter carport.  Next step finishing the walls (cement plaster) inside and out. House Construction Expense Our Philippine house building project – construction cost report as of 5-22-10. Roof completed 1/1/2010 through 5/22/2010 (in U.S. Dollars) Equipment 2,545.19 (Most to be sold at end of project. Concrete vibrator