House Construction Expense 1/1/2010 through 5/22/2010 (in U.S. Dollars) House Construction 40,904.32 Equipment 2,545.19 Labor 7,095.75 Materials 30,251.73 Soft Costs 1,011.65 OVERALL TOTAL 40,904.32 Includes stockpiled materials, almost all electrical and plumbing supplies and fixtures.  Electrical work about 50% complete.  Plumbing about 75% complete. Includes work on 35 square meter carport.  Next step finishing the walls (cement plaster) inside and out. House Construction Expense Our Philippine house building project – construction cost report as of 5-22-10. Roof completed 1/1/2010 through 5/22/2010 (in U.S. Dollars) Equipment 2,545.19 (Most to be sold at end of project. Concrete vibrator

How much does it cost to build a house in the Philippines?  Here’s our experience, month by month. February 20, 2010. Construction cost report for our Philippine House Project.   Thirty work days so far. Here’s what the house looks like after thirty days of work: After thirty work days… House Construction Expense – YTD:2 1/1/2010 through 2/21/2010 (in U.S. Dollars) Category Description 1/1/2010- 2/21/2010 House Construction 15,788.01 Equipment 2,345.72 Labor 2,489.01 Materials 10,104.24 Soft Costs 849.04 OVERALL TOTAL 15,788.01 H ouse Construction Expense Summary 1/1/2010 through 2/21/2010 (in U.S. Dollars) Equipment 2,345.72 Labor 2,489.01 Materials 10,104.24 Soft Costs (architecture, permits) 849.04 OVERALL TOTAL SO FAR: $15,788.01 Number of workers: 16 Current cost of cement: P212 ———————————————————————————————————————— March 12, 2010 construction expense report . Covers 45 work days since beginning of construction on January 18, 2010. House Construction Expense – YTD:2 1/1/2010 through 3/12/2010 (in U.S. Dollars) Category Description 1/1/2010- 3/12/2010 House Construction 22,843.05 Equipment 2,350.47 Labor 3,658.36 Materials 15,908.79 Soft Costs 925.43 OVERALL TOTAL 22,843.05 House after 45 days of work and about one million pesos. March 12, 2010 Total House Construction Expense to date  (in U.S. Dollars) Equipment 2,350.47 (10.29% of total) Labor…

Building our house in the Philippines. January 31, 2010.  We’ve just ended the first two weeks of construction.  We’re generally pleased with the progress.  We have thirteen workers on our crew including two foremen.  I’m on-site most of the time so there are three “bosses”. So far we’ve spent about $8,000 including “soft costs” (architecture, permits), equipment, materials and labor.  We’d like to keep our total cost to about P15,000 per square meter or about $50,000 for the 150 square meter house.  Every day one faces decision which affect the cost.  Should we use 6″ block for a stronger house — it only costs a P30,000 pesos more!  Should the concrete floor be a bit thicker to reduce the chance of cracking?  Should we use 1/4″ thick angle bar in building our roof trusses or the thinner…