Our Philippine House Building Project House Construction Expense Report – Sept. 25, 2010 Granite installed For those of you…

Being your own contractor in the Philippines.  Our Philippine house building project is almost  complete.  After our unhappy experiences with hiring an architect to build our perimeter fence (see _____)  we decided to hire our own crew to build our house.  We hired an architect to do the plans and to come for site visits on an as-needed basis.  We shopped for our own materials and supervised the work with help from a foreman. Was this a success?  It looks like it’s going to cost us about 2.5 million pesos for our 150 square meter house or about P16,500 per square meter.  Houses can be built for that amount or less, but we tried to use top quality materials, so we feel as though we have gotten a…

How much does it cost to build a house in the Philippines?  Here’s our experience, month by month. February 20, 2010. Construction cost report for our Philippine House Project.   Thirty work days so far. Here’s what the house looks like after thirty days of work: After thirty work days… House Construction Expense – YTD:2 1/1/2010 through 2/21/2010 (in U.S. Dollars) Category Description 1/1/2010- 2/21/2010 House Construction 15,788.01 Equipment 2,345.72 Labor 2,489.01 Materials 10,104.24 Soft Costs 849.04 OVERALL TOTAL 15,788.01 H ouse Construction Expense Summary 1/1/2010 through 2/21/2010 (in U.S. Dollars) Equipment 2,345.72 Labor 2,489.01 Materials 10,104.24 Soft Costs (architecture, permits) 849.04 OVERALL TOTAL SO FAR: $15,788.01 Number of workers: 16 Current cost of cement: P212 ———————————————————————————————————————— March 12, 2010 construction expense report . Covers 45 work days since beginning of construction on January 18, 2010. House Construction Expense – YTD:2 1/1/2010 through 3/12/2010 (in U.S. Dollars) Category Description 1/1/2010- 3/12/2010 House Construction 22,843.05 Equipment 2,350.47 Labor 3,658.36 Materials 15,908.79 Soft Costs 925.43 OVERALL TOTAL 22,843.05 House after 45 days of work and about one million pesos. March 12, 2010 Total House Construction Expense to date  (in U.S. Dollars) Equipment 2,350.47 (10.29% of total) Labor…

Building our house in the Philippines. Buying our construction equipment in Iloilo.  Delivered, premixed concrete is rarely used in residential construction in the Philippine provinces.  In fact, many houses are built without even a cement mixer.  The concrete is mixed on the ground by workers with shovels. When we were considering a two story house, we were certain a gas powered mixer would be a good investment in the quality of the concrete and the safety of our house and ourselves.  This is…